  4 June 2008

MEDUPI POWER STATION - MAIN CIVIL WORKS AWARD

The Medupi Power Station Joint Venture, comprising Murray & Roberts Construction, Concor and Grinaker-LTA has secured the main civil work package for the Medupi Power Station, 15 km west of Lephalale in the Limpopo province.

The Medupi Power Station is the first new coal fired power station to be built in twenty years and when fully commissioned will generate approximately 4,500 MW and be the biggest coal fired plant in the world.

The scope of work for this 52 month project will include the civil works associated with the main power island and the ancillary structures. In total, some 550 000 m3 of concrete, 600 000 m2 of formwork and 60 000 t of reinforcing steel will be used. Site establishment will start in May 2008 and the scheduled contract completion is 2012. The project value is approximately three billion rand.

Collectively, the joint venture amasses the majority of the civil industry capability and represents the majority of the intellectual property and experience on the building of power stations within the civil construction fraternity in South Africa.

An important aspect of the Joint Venture proposal was its value offering to uplift CIDB (Construction Industry Development Board) Level 6 to 8 BEE contractors.

The extremely short delivery time increases the complexity and challenges faced on this project. A challenge posed by the project is the 38 other work packages that will need to seamlessly interface with the main civil contractor’s work.